Update: March 22, 2022
Clallam Bay
Crews reopened State Route 112 at Clallam Bay at 6 p.m. Monday, March 21 to two-way travel for the first time since November 2021 following a massive landslide and regionwide flooding. Travelers may encounter intermittent lane closures with flaggers as crew complete final guardrail installation and hillside seeding. A portion of the highway will remain a temporary gravel surface until crews are cleared to pave it after the highway dropped 6 inches. Engineering geologists continue to monitor the new roadway settlement, which was discovered on Thursday, March 17. The temporary detour on Eagle Crest Way has been removed and returned to private property owners. We would like to thank travelers, residents, the Makah Tribe, and property owners of Eagle Crest Way for their cooperation and support during this closure.
Jim Creek
Construction at milepost 32 further east is expected to begin late March. More information about this emergency repair project is available online.
Update: March 18, 2022
Clallam Bay
As our emergency contractor was finalizing re-grade work at milepost 15.8 near Clallam Bay to reopen the highway on Thursday, March 17, crews discovered additional settlement had occurred. The highway has settled approximately six inches since the roadway repairs had been made. The dynamics of large landslides are complex, and because SR 112 sits on an active slide zone, we are taking immediate action. Our geotechnical engineers are on site today and will recommend next steps for reopening. Crews anticipate additional repairs will take place the week of March 21 to reopen the highway as quickly as possible. Travelers will continue to detour using Eagle Crest Way around the slide until further notice.
Update: Tuesday, March 1, 2022
Clallam Bay
Our emergency contractor continues to make good progress clearing milepost 15.8. As of Monday, Feb. 28, crews hauled 39,700 cubic yards of debris from the hillside and roadway. Next steps include erosion control measures and replacing a damaged culvert beneath the highway. From there, crews will rebuild the highway, install new guardrail, and complete hillside seeding. We expect to reopen SR 112 at Clallam Bay in the coming weeks. Project webpage: https://wsdot.wa.gov/construction-planning/search-projects/sr-112-clallam-bay-emergency-repairs
Jim Creek
The design solution at Jim Creek is more complex. We expect to have a contract out to bidders by March 4, 2022, for a bid opening in mid-March. With a rapid award and execution process, crews could mobilize and begin work later this month. Work will include ground drainage measures, improved surface drainage, and rebuilding the roadway. Construction should last through spring 2022. Project webpage: https://wsdot.wa.gov/construction-planning/search-projects/sr-112-jim-creek-west-emergency-repairs
Update: Feb. 15, 2022
Clallam Bay
At milepost 15.85, our emergency contractor is making progress towards reopening SR 112. Crews have removed 15,000 cubic yards of hillside debris. They are on schedule to reopen SR 112 at Clallam Bay in early spring 2022. Until then, travelers will continue to use the bypass route, Eagle Crest Way which is maintained weekly by construction crews.
Jim Creek
Further east at milepost 32, design solutions for Jim Creek are more complex. Through a rapid award and execution process, we anticipate construction to begin the week of March 7. Work will include ground drainage measures, improved surface drainage, and rebuilding the roadway. Repairs are expected to take 8 weeks to complete.
Update: Feb. 1, 2022
Clallam Bay
This week, our contractor mobilized heavy equipment to milepost 15.8 and will begin work to install fencing and prepare the waste site. Eagle Crest Way remains open to all traffic while repairs to the Clallam Bay slide are underway. Work is expected to take 8 weeks to complete.
Jim Creek
Our design engineers are finalizing contract plans. We expect to solicit bids the week of Feb. 14, and with rapid award and execution, begin work as soon as the week of Feb. 28. Construction to reopen the Jim Creek slide includes ground drainage improvements, debris removal, guardrail installation and rebuilding the highway. Work is expected to take 8 weeks to complete.
Update: Jan. 18, 2022
Clallam Bay
On Tuesday, Jan. 18, we solicited bids to five emergency contractors related to long-term repairs to State Route 112 at milepost 15.8 near Clallam Bay. We expect to receive bids back on Thursday, Jan. 20 and, with a rapid award and execution process, start work the week of Jan. 24.
Work is expected to take 4-8 weeks to complete. The temporary bypass route via Eagle Crest Way will remain open and maintained by a separate contractor until repairs to the Clallam Bay site are complete.
Jim Creek
We are awaiting final design recommendations from our engineering geologists on long-term repairs to reopen SR 112 at milepost 32 near Jim Creek. Those recommendations determine our final plans and proposal documents we provide to contractors.
We expect to solicit bids on Friday, Feb. 4. With rapid award and execution of this emergency contract, we anticipate work to begin the week of Feb. 14.
Work is expected to take 4-8 weeks to complete
Update: Jan. 4, 2022
Clallam Bay
Final engineering, hydraulic design, and survey work to reopen SR 112 at milepost 15.8 near Clallam Bay is almost complete. We have obtained emergency entry permits to work along the hillside away from state right of way. We are pursuing long-term design solutions to reduce the frequency and severity of potential future slide activity.
With the recent winter weather behind us, our emergency contractor will grade the Eagle Crest Way bypass route on Wednesday, Jan. 5. Grading, patching, and plowing will continue through Friday, Jan. 7. Travelers should expect one-way alternating conditions with flaggers while repairs are underway to the route.
We expect to have a contract available for competitive bids the week of Jan. 10. Bid opening follows the next week. Because SR 112 is a vital link for the local community, we are conducting an expedited bid and award process of five days. We expect to have a contractor on board to begin site mobilization the week of Jan. 24.
Work to reopen the highway includes removing hillside and roadway debris, slope stabilization efforts, roadway repairs, installation of new guardrail, replacement of damaged culvert pipes, erosion control, and seeding.
A contract for the Clallam Bay slide will also include maintenance of Eagle Crest Way until work is complete. Construction should last up to 8 weeks. Eagle Crest Way will remain open to all traffic during construction.
Jim Creek
Further east, the repairs necessary to reopen SR 112 at milepost 32 near Jim Creek are more complex due to the nature of the slide zone. The work for Jim Creek will be a separate contract from the Clallam Bay slide. We expect to advertise for competitive bids in Feb. 2022. Right of way permitting and design work is underway through late January. Travelers will continue to detour around the slide via SR 113 and US 101 until further notice. Repairs to Jim Creek should take up to 8 weeks.
Please continue to follow our blog and social media channels for the latest updates on SR 112.
Update: Dec. 23, 2021
State Route 112 at milepost 15.8 near Clallam Bay remains blocked after more than 300 feet of the hillside toppled onto the highway last month. We continue to maintain the temporary bypass route at Eagle Crest Way to ensure nearby communities have access and necessary supplies. Maintenance crews smoothed the surface again last Thursday with several truckloads of gravel. Please travel slowly in the area to help keep the bypass roadway smoother.
On Monday, Dec. 20, emergency contractor Bruch and Bruch Construction, Inc. took over maintaining the temporary bypass road. Bruch and Bruch will grade the gravel road and monitor the temporary traffic signal until repairs to the Clallam Bay slide site are complete. A tentative schedule for releasing an emergency contract to repair the Clallam Bay and Jim Creek sites is underway now, as well as right-of-way permitting, survey and maintenance work.
Update: Dec. 14, 2021
SR 112 at milepost 15.8 near Clallam Bay remains saturated and unstable. Our engineering geologists have completed their preliminary investigations and expect construction to take approximately four to eight weeks to reopen the highway once we can get started clearing the roadway of debris and stabilizing the slope.
Further east, repairs to the nearly two and a half feet of roadway settlement at Jim Creek (milepost 32) are complex. Our crews have installed monitoring devices at Jim Creek to evaluate earth movement. After it's stable, we can begin the work to reopen the highway, and we expect the work to reopen SR 112 at Jim Creek to take four to six weeks.
Our designers, engineering geologists and construction experts are working together to develop a timeline for an emergency contract. We'll update this blog with more information about the process and contracts when we have it.
Update: Dec. 6, 2021
Crews completed repairs to a temporary bypass route at Eagle Crest Way on Friday, Dec. 3. Crews will maintain and operate the bypass while repairs to SR 112 are underway. Unfortunately, the Clallam Bay slide (milepost 15.8) is still moving. Additional debris fell Sunday, Nov. 28, extending the slide area another 200 feet across the roadway.
Engineering geologists are evaluating the Clallam Bay site to encompass new debris that includes drainage solutions prior to excavation work. While design work remains underway for both Clallam Bay and Jim Creek sites, project engineers hope to have a contract available for competitive bids in early 2022. Our team is working with local property owners to obtain temporary right-of-way permits to allow crews access to areas where repairs will be necessary. We will continue to update this blog as we know more information.
By Stefanie Randolph
It was a rough November for Clallam County, as you may have heard. A strong storm closed every state highway in the county on Nov. 15, keeping road crews busy trying to assess and clear debris and keeping travelers either stuck or finding long alternate routes.
While our crews worked around the clock to reopen as many roadways as possible – pulling crews from Aberdeen and Port Orchard to help – State Route 112 remains closed, and because it will require some extensive repairs, it could be a while before it fully reopens.
Why? Some of these pictures tell the story. An initial slide near Clallam Bay was 275 feet wide and covered 325 feet of the highway. And it's still moving – more debris fell this past Sunday, Nov. 28, extending the slide area another 200 feet across the roadway. In short, it's a really big slide, and still active and potentially dangerous area.
 |
Left: The initial slide
covering SR 112 near Clallam Bay was 275 feet wide and covered 325 feet of
highway. Right: Since the first slide, more debris has fallen onto the roadway at SR 112 near Clallam Bay, preventing crews from safely moving into the area. |
Our geologists are regularly monitoring the site but until the hillside is stable, we can't safely go in and clear debris or begin repairs. With Gov. Inslee's emergency declaration, we are able to expedite the process – including finding an emergency contractor – but there are still several steps that have to be taken, including designing a safe repair plan. We don't have a timeline yet for all of this as it's dependent on the site stabilizing enough for crews to move in.
Temporary help
The good news is we have restored some local travel. Earlier this week, we secured permits to establish a temporary bypass route around the slide area to accommodate local traffic including school buses and commercial vehicles. The route uses a private two-lane road with one-way alternating in one spot. On Wednesday, Dec. 1 and Thursday, Dec. 2 there will be some delays while we do some maintenance in that area. We'll maintain and repair this road until SR 112 is reopened. There will be signs to help travelers get through the area.
 |
Left: Another 200 more feet of SR 112 have been covered by slide debris after the initial slide covered 325 feet of roadway. Right: Near Jim Creek, SR 112 has dropped about 2 feet and will need extensive repairs to fix. |
What about Jim Creek?
The Clallam Bay site isn't the only spot that remains closed. SR 112 at milepost 32 near Jim Creek is also closed after the storm resulted in standing water, roadway settlement and a debris slide. Once our crews were able to safely respond to that area, they found that the road had dropped more than 2 feet and will also require an emergency contract to reopen.
This is the same area where we recently finished repairs after a storm in Dec. 2020 dropped the highway almost 13 feet.
Progress
After November's initial storm, SR 112 was also closed between mileposts 0-11 near Neah Bay. Our crews were able to clear that stretch. Flooding of the Hoko River prevented crews from evaluating damage west of milepost 12 until late Tuesday, November 16. Once they were able to get safely through, maintenance crews cleared 14 sites within the 11-mile section and reopened it on November 17. They removed debris from small slides and cleared drainage culverts to prevent flowing of further debris and damage to the roadway.
Real-time travel information is available on our updated travel center map and travelers can sign up for project email alerts. Once we know more, we will share that info but in the meantime, please do not go beyond road closure signs and stay alert for road workers.